671 - Goulburn Giles Court Redevelopment
Nylige bulletiner
  • 19th mai 2025, UPCOMING WORKS THIS WEEK: 19-23rd May



    Cutting of floors & trenches for drainage works & wet areas

    in ground pipe install

    floor grinding prepping

    demo detailing

    A/C De lap & modifications to existing duct




    KEY HAZARDS:

    Saw cutting to concrete floor

    Open trench's and wet areas internally

    Hazardous Manual Tasks,

    Slips, Trips and Falls, Falling

    Objects, Cuts and Abrasions,
    Use of Electrical Tools and
    Equipment, Dust, etc
    Exposure to Respirable
    Crystalline Silica (RCS) –
    inhaling RCS can lead to
    silicosis



    DISCONNECTIONS :

    ACTION-ED PRIOR TO DEMO

    water --YES
    power---YES
    fire --YES
    security---YES
    A/c ---YES


    SERVICES INVESTIGATIONS:

    For new wet area connections to existing below floor slab ( Actioned )


    UNDERGROUND SERVICES :

    Before carrying out any underground work, locate services using
    Before You Dig Australia, a services locator, non-destructive potholing, potholing by hand
    and by taking the other precautions identified in the Code of Practice: Work in the Vicinity of
    Overhead and Underground Electric Lines



    PERMITS:

    Permits are required to be uploaded on hammertech ready for approval prior to any works commencing onsite

    FOR:

    Demolition
    Hot works
    Excavation / cutting / coring etc



    ELECTRICAL SAFETY:

    Temp boards in place for the construction works :

    Treat all cables as live if in doubt ASK !
    Ensure all leads / tools are tagged


    HOUSEKEEPING:

    It is everyone's responsibility to insure lunch room & toilets are kept clean.

    Ensure everyone places there food / rubbish in the bins and not thrown around site road or gardens

    Ensure your work area is cleaned everyday prior to leaving site.

    PLANT & EQUIPMENT:

    Please ensure all plant is uploaded on hammertech ready for approval prior to bringing to site


    WHEN LOADING OUT DURING DEMO BE AWARE :

    collision/striking with other
    plant driving around the site
    workers or public on foot
    Spotter to be inplace
    bunt of work areas where required


    SITE RULES & PPE REQUIREMENTS:

    Park is at the front of the job, keep access clear for residents,
    Ensure you are always wearing the site requirements PPE which is Hardhat, hi vis and
    safety boots

    NO SMOKING ONSITE:
    This includes smoking in front & back of the building !!!

    Tillegg :
    Sawcutting & Concrete Removal Mark-up.pdf
    250517 Services Search Report Giles Court.pdf
  • 06th mai 2025, WEEKLY BULLETIN GILES COURT 05-05-25

    UPCOMING WORKS THIS WEEK:


    Structural install of framing & bracing in ceiling void

    Timber noggin to existing walls

    cutting off floors & trenches for drainage works

    floor grinding prepping

    ongoing demo detailing throughout




    KEY HAZARDS:


    Hazardous Manual Tasks,
    Slips, Trips and Falls, Falling
    Objects, Cuts and Abrasions,
    Use of Electrical Tools and
    Equipment, Dust, etc
    Exposure to Respirable
    Crystalline Silica (RCS) –
    inhaling RCS can lead to
    silicosis



    DISCONNECTIONS :

    ACTION-ED PRIOR TO DEMO

    water --YES
    power---YES
    fire --YES
    security---YES
    A/c ---YES


    SERVICES INVESTIGATIONS:

    For new wet area connections to existing below floor slab


    UNDERGROUND SERVICES :

    Before carrying out any underground work, locate services using
    Before You Dig Australia, a services locator, non-destructive potholing, potholing by hand
    and by taking the other precautions identified in the Code of Practice: Work in the Vicinity of
    Overhead and Underground Electric Lines



    PERMITS:

    Permits are required to be uploaded on hammertech ready for approval prior to any works commencing onsite

    FOR:

    Demolition
    Hot works
    Excavation / cutting / coring etc



    ELECTRICAL SAFETY:

    Temp boards in place for the construction works :

    Treat all cables as live if in doubt ASK !
    Ensure all leads / tools are tagged


    HOUSEKEEPING:

    It is everyone's responsibility to insure lunch room & toilets are kept clean.

    Ensure everyone places there food / rubbish in the bins and not thrown around site road or gardens

    Ensure your work area is cleaned everyday prior to leaving site.

    PLANT & EQUIPMENT:

    Please ensure all plant is uploaded on hammertech ready for approval prior to bringing to site


    WHEN LOADING OUT DURING DEMO BE AWARE :

    collision/striking with other
    plant driving around the site
    workers or public on foot
    Spotter to be inplace
    bunt of work areas where required


    SITE RULES & PPE REQUIREMENTS:

    Park is at the front of the job, keep access clear for residents,
    Ensure you are always wearing the site requirements PPE which is Hardhat, hi vis and
    safety boots

    NO SMOKING ONSITE:
    This includes smoking in front & back of the building !!!

  • 22nd april 2025, WEEKLY BULLETIN 22-04-25

    UPCOMING WORKS THIS WEEK:

    NOTE:

    PART OF BLADE WALL TO BE LEFT STANDING ON EASTERN SIDE OF BLD FOR TEMP SUPPORT TO EXTERIOR WALL


    Demo of internal walls, removal of ceiling insulation , door openings etc


    KEY HAZARDS:

    BRICK WALL , HOLDING UP ROOF VALLEY DO NOT REMOVE UNLESS APPROVED BY PBG


    Hazardous Manual Tasks,
    Slips, Trips and Falls, Falling
    Objects, Cuts and Abrasions,
    Use of Electrical Tools and
    Equipment, Dust, etc
    Exposure to Respirable
    Crystalline Silica (RCS) –
    inhaling RCS can lead to
    silicosis



    DISCONNECTIONS :

    ACTION-ED PRIOR TO DEMO

    water --YES
    power---YES
    fire --YES
    security---YES
    A/c ---YES


    SERVICES INVESTIGATIONS:

    For new wet area connections to existing below floor slab


    UNDERGROUND SERVICES :

    Before carrying out any underground work, locate services using
    Before You Dig Australia, a services locator, non-destructive potholing, potholing by hand
    and by taking the other precautions identified in the Code of Practice: Work in the Vicinity of
    Overhead and Underground Electric Lines



    PERMITS:

    Permits are required to be uploaded on hammertech ready for approval prior to any works commencing onsite

    FOR:

    Demolition
    Hot works
    Excavation / cutting / coring etc



    ELECTRICAL SAFETY:

    Temp boards in place for the construction works :

    Treat all cables as live if in doubt ASK !
    Ensure all leads / tools are tagged


    HOUSEKEEPING:

    It is everyone's responsibility to insure lunch room & toilets are kept clean.

    Ensure everyone places there food / rubbish in the bins and not thrown around site road or gardens

    Ensure your work area is cleaned everyday prior to leaving site.

    PLANT & EQUIPMENT:

    Please ensure all plant is uploaded on hammertech ready for approval prior to bringing to site


    WHEN LOADING OUT DURING DEMO BE AWARE :

    collision/striking with other
    plant driving around the site
    workers or public on foot
    Spotter to be inplace
    bunt of work areas where required


    SITE RULES & PPE REQUIREMENTS:

    Park is at the front of the job, keep access clear for residents,
    Ensure you are always wearing the site requirements PPE which is Hardhat, hivis and
    safety boots

    NO SMOKING ONSITE:

    Client has requested that workers don,t smoke in-front of job site (Bradley st )
    Do so, ON THE OPPOSITE SIDE of the road
    thank you for your cooperation

Nettstedets værmelding
Vær på anleggsted

Sist oppdatert kl.: 18:21
Temperatur: 17C (App 17C)
Vindfart: 9KMH
Maks. Vind: 9KMH @18:21
Regn side 09.00: 0,8mm


Observasjon hentet fra - Bureau of Meteorology
Observasjonssted - Goulburn, NEW SOUTH WALES
Tidssone - austaustralsk standardtid
Værmelding – fredag, 16 januar

Showers.
Min.: 14C Maks.: 20C
Sjanse for regn: 80%
Forventet nedbør: 1 til 20mm


Værmelding hentet fra – Bureau of Meteorology
Sted for værmelding – Goulburn, NEW SOUTH WALES
Tidssone - austaustralsk standardtid
I morgen - laurdag, 17 januar

Shower or two.
Min.: 13C Maks.: 20C
Sjanse for regn: 70%
Forventet nedbør: 0 til 5mm


Viktige dokumenter for anleggsplassen
Ny på anleggsplassen?

Vet du om PVU-kravene for dette anlegget?

Sørg for at du har riktig sikkerhetsutstyr for den første dagen på anleggsplassen.

Se PPE-kravene til nettstedet

Kom i gang med arbeidet tidligere når du ankommer anleggsplassen.

Fullfør nettstedsregistreringen din online når det passer deg og spar tid.

Start registrering

Ny på anleggsplassen?

Vet du om PVU-kravene for dette anlegget?

Sørg for at du har riktig sikkerhetsutstyr for den første dagen på anleggsplassen.

Se PPE-kravene til nettstedet

Ny på anleggsplassen?

Kom i gang med arbeidet tidligere når du ankommer anleggsplassen.

Fullfør nettstedsregistreringen din online når det passer deg og spar tid.

Start registrering

;