19th mayo 2025, UPCOMING WORKS THIS WEEK: 19-23rd May
Archivos adjuntos :
Cutting of floors & trenches for drainage works & wet areas
in ground pipe install
floor grinding prepping
demo detailing
A/C De lap & modifications to existing duct
KEY HAZARDS:
Saw cutting to concrete floor
Open trench's and wet areas internally
Hazardous Manual Tasks,
Slips, Trips and Falls, Falling
Objects, Cuts and Abrasions,
Use of Electrical Tools and
Equipment, Dust, etc
Exposure to Respirable
Crystalline Silica (RCS) –
inhaling RCS can lead to
silicosis
DISCONNECTIONS :
ACTION-ED PRIOR TO DEMO
water --YES
power---YES
fire --YES
security---YES
A/c ---YES
SERVICES INVESTIGATIONS:
For new wet area connections to existing below floor slab ( Actioned )
UNDERGROUND SERVICES :
Before carrying out any underground work, locate services using
Before You Dig Australia, a services locator, non-destructive potholing, potholing by hand
and by taking the other precautions identified in the Code of Practice: Work in the Vicinity of
Overhead and Underground Electric Lines
PERMITS:
Permits are required to be uploaded on hammertech ready for approval prior to any works commencing onsite
FOR:
Demolition
Hot works
Excavation / cutting / coring etc
ELECTRICAL SAFETY:
Temp boards in place for the construction works :
Treat all cables as live if in doubt ASK !
Ensure all leads / tools are tagged
HOUSEKEEPING:
It is everyone's responsibility to insure lunch room & toilets are kept clean.
Ensure everyone places there food / rubbish in the bins and not thrown around site road or gardens
Ensure your work area is cleaned everyday prior to leaving site.
PLANT & EQUIPMENT:
Please ensure all plant is uploaded on hammertech ready for approval prior to bringing to site
WHEN LOADING OUT DURING DEMO BE AWARE :
collision/striking with other
plant driving around the site
workers or public on foot
Spotter to be inplace
bunt of work areas where required
SITE RULES & PPE REQUIREMENTS:
Park is at the front of the job, keep access clear for residents,
Ensure you are always wearing the site requirements PPE which is Hardhat, hi vis and
safety boots
NO SMOKING ONSITE:
This includes smoking in front & back of the building !!!
Sawcutting & Concrete Removal Mark-up.pdf
250517 Services Search Report Giles Court.pdf
-
06th mayo 2025, WEEKLY BULLETIN GILES COURT 05-05-25
UPCOMING WORKS THIS WEEK:
Structural install of framing & bracing in ceiling void
Timber noggin to existing walls
cutting off floors & trenches for drainage works
floor grinding prepping
ongoing demo detailing throughout
KEY HAZARDS:
Hazardous Manual Tasks,
Slips, Trips and Falls, Falling
Objects, Cuts and Abrasions,
Use of Electrical Tools and
Equipment, Dust, etc
Exposure to Respirable
Crystalline Silica (RCS) –
inhaling RCS can lead to
silicosis
DISCONNECTIONS :
ACTION-ED PRIOR TO DEMO
water --YES
power---YES
fire --YES
security---YES
A/c ---YES
SERVICES INVESTIGATIONS:
For new wet area connections to existing below floor slab
UNDERGROUND SERVICES :
Before carrying out any underground work, locate services using
Before You Dig Australia, a services locator, non-destructive potholing, potholing by hand
and by taking the other precautions identified in the Code of Practice: Work in the Vicinity of
Overhead and Underground Electric Lines
PERMITS:
Permits are required to be uploaded on hammertech ready for approval prior to any works commencing onsite
FOR:
Demolition
Hot works
Excavation / cutting / coring etc
ELECTRICAL SAFETY:
Temp boards in place for the construction works :
Treat all cables as live if in doubt ASK !
Ensure all leads / tools are tagged
HOUSEKEEPING:
It is everyone's responsibility to insure lunch room & toilets are kept clean.
Ensure everyone places there food / rubbish in the bins and not thrown around site road or gardens
Ensure your work area is cleaned everyday prior to leaving site.
PLANT & EQUIPMENT:
Please ensure all plant is uploaded on hammertech ready for approval prior to bringing to site
WHEN LOADING OUT DURING DEMO BE AWARE :
collision/striking with other
plant driving around the site
workers or public on foot
Spotter to be inplace
bunt of work areas where required
SITE RULES & PPE REQUIREMENTS:
Park is at the front of the job, keep access clear for residents,
Ensure you are always wearing the site requirements PPE which is Hardhat, hi vis and
safety boots
NO SMOKING ONSITE:
This includes smoking in front & back of the building !!! -
22nd abril 2025, WEEKLY BULLETIN 22-04-25
UPCOMING WORKS THIS WEEK:
NOTE:
PART OF BLADE WALL TO BE LEFT STANDING ON EASTERN SIDE OF BLD FOR TEMP SUPPORT TO EXTERIOR WALL
Demo of internal walls, removal of ceiling insulation , door openings etc
KEY HAZARDS:
BRICK WALL , HOLDING UP ROOF VALLEY DO NOT REMOVE UNLESS APPROVED BY PBG
Hazardous Manual Tasks,
Slips, Trips and Falls, Falling
Objects, Cuts and Abrasions,
Use of Electrical Tools and
Equipment, Dust, etc
Exposure to Respirable
Crystalline Silica (RCS) –
inhaling RCS can lead to
silicosis
DISCONNECTIONS :
ACTION-ED PRIOR TO DEMO
water --YES
power---YES
fire --YES
security---YES
A/c ---YES
SERVICES INVESTIGATIONS:
For new wet area connections to existing below floor slab
UNDERGROUND SERVICES :
Before carrying out any underground work, locate services using
Before You Dig Australia, a services locator, non-destructive potholing, potholing by hand
and by taking the other precautions identified in the Code of Practice: Work in the Vicinity of
Overhead and Underground Electric Lines
PERMITS:
Permits are required to be uploaded on hammertech ready for approval prior to any works commencing onsite
FOR:
Demolition
Hot works
Excavation / cutting / coring etc
ELECTRICAL SAFETY:
Temp boards in place for the construction works :
Treat all cables as live if in doubt ASK !
Ensure all leads / tools are tagged
HOUSEKEEPING:
It is everyone's responsibility to insure lunch room & toilets are kept clean.
Ensure everyone places there food / rubbish in the bins and not thrown around site road or gardens
Ensure your work area is cleaned everyday prior to leaving site.
PLANT & EQUIPMENT:
Please ensure all plant is uploaded on hammertech ready for approval prior to bringing to site
WHEN LOADING OUT DURING DEMO BE AWARE :
collision/striking with other
plant driving around the site
workers or public on foot
Spotter to be inplace
bunt of work areas where required
SITE RULES & PPE REQUIREMENTS:
Park is at the front of the job, keep access clear for residents,
Ensure you are always wearing the site requirements PPE which is Hardhat, hivis and
safety boots
NO SMOKING ONSITE:
Client has requested that workers don,t smoke in-front of job site (Bradley st )
Do so, ON THE OPPOSITE SIDE of the road
thank you for your cooperation
Tiempo en Obra actual
Última actualización el: 6:21 PM
Temperatura: 17C (Aplicación 17C)
Velocidad del viento: 9MPH
Máx. Viento: 9MPH @6:21 PM
Lluvia desde las 9 a.m.: 0.8mm
Lugar de observación - Goulburn, NEW SOUTH WALES
Zona horaria - hora estándar de Australia oriental
Pronóstico - viernes, 16 enero
Showers.
Mín: 14C Máx: 20C
Probabilidad de lluvia: 80%
Se esperan precipitaciones: 1 para 20mm
Lugar de la previsión - Goulburn, NEW SOUTH WALES
Zona horaria - hora estándar de Australia oriental
Mañana - sábado, 17 enero
Shower or two.
Mín: 13C Máx: 20C
Probabilidad de lluvia: 70%
Se esperan precipitaciones: 0 para 5mm
¿Conoce los requisitos de PPE para esta Obra?
Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.
Empiece a trabajar en cuanto llegue a la obra.
Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.
¿Conoce los requisitos de PPE para esta Obra?
Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.
Empiece a trabajar en cuanto llegue a la obra.
Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.