19th Haratua 2025, UPCOMING WORKS THIS WEEK: 19-23rd May
Ngā Āpitihanga :
Cutting of floors & trenches for drainage works & wet areas
in ground pipe install
floor grinding prepping
demo detailing
A/C De lap & modifications to existing duct
KEY HAZARDS:
Saw cutting to concrete floor
Open trench's and wet areas internally
Hazardous Manual Tasks,
Slips, Trips and Falls, Falling
Objects, Cuts and Abrasions,
Use of Electrical Tools and
Equipment, Dust, etc
Exposure to Respirable
Crystalline Silica (RCS) –
inhaling RCS can lead to
silicosis
DISCONNECTIONS :
ACTION-ED PRIOR TO DEMO
water --YES
power---YES
fire --YES
security---YES
A/c ---YES
SERVICES INVESTIGATIONS:
For new wet area connections to existing below floor slab ( Actioned )
UNDERGROUND SERVICES :
Before carrying out any underground work, locate services using
Before You Dig Australia, a services locator, non-destructive potholing, potholing by hand
and by taking the other precautions identified in the Code of Practice: Work in the Vicinity of
Overhead and Underground Electric Lines
PERMITS:
Permits are required to be uploaded on hammertech ready for approval prior to any works commencing onsite
FOR:
Demolition
Hot works
Excavation / cutting / coring etc
ELECTRICAL SAFETY:
Temp boards in place for the construction works :
Treat all cables as live if in doubt ASK !
Ensure all leads / tools are tagged
HOUSEKEEPING:
It is everyone's responsibility to insure lunch room & toilets are kept clean.
Ensure everyone places there food / rubbish in the bins and not thrown around site road or gardens
Ensure your work area is cleaned everyday prior to leaving site.
PLANT & EQUIPMENT:
Please ensure all plant is uploaded on hammertech ready for approval prior to bringing to site
WHEN LOADING OUT DURING DEMO BE AWARE :
collision/striking with other
plant driving around the site
workers or public on foot
Spotter to be inplace
bunt of work areas where required
SITE RULES & PPE REQUIREMENTS:
Park is at the front of the job, keep access clear for residents,
Ensure you are always wearing the site requirements PPE which is Hardhat, hi vis and
safety boots
NO SMOKING ONSITE:
This includes smoking in front & back of the building !!!
Sawcutting & Concrete Removal Mark-up.pdf
250517 Services Search Report Giles Court.pdf
-
06th Haratua 2025, WEEKLY BULLETIN GILES COURT 05-05-25
UPCOMING WORKS THIS WEEK:
Structural install of framing & bracing in ceiling void
Timber noggin to existing walls
cutting off floors & trenches for drainage works
floor grinding prepping
ongoing demo detailing throughout
KEY HAZARDS:
Hazardous Manual Tasks,
Slips, Trips and Falls, Falling
Objects, Cuts and Abrasions,
Use of Electrical Tools and
Equipment, Dust, etc
Exposure to Respirable
Crystalline Silica (RCS) –
inhaling RCS can lead to
silicosis
DISCONNECTIONS :
ACTION-ED PRIOR TO DEMO
water --YES
power---YES
fire --YES
security---YES
A/c ---YES
SERVICES INVESTIGATIONS:
For new wet area connections to existing below floor slab
UNDERGROUND SERVICES :
Before carrying out any underground work, locate services using
Before You Dig Australia, a services locator, non-destructive potholing, potholing by hand
and by taking the other precautions identified in the Code of Practice: Work in the Vicinity of
Overhead and Underground Electric Lines
PERMITS:
Permits are required to be uploaded on hammertech ready for approval prior to any works commencing onsite
FOR:
Demolition
Hot works
Excavation / cutting / coring etc
ELECTRICAL SAFETY:
Temp boards in place for the construction works :
Treat all cables as live if in doubt ASK !
Ensure all leads / tools are tagged
HOUSEKEEPING:
It is everyone's responsibility to insure lunch room & toilets are kept clean.
Ensure everyone places there food / rubbish in the bins and not thrown around site road or gardens
Ensure your work area is cleaned everyday prior to leaving site.
PLANT & EQUIPMENT:
Please ensure all plant is uploaded on hammertech ready for approval prior to bringing to site
WHEN LOADING OUT DURING DEMO BE AWARE :
collision/striking with other
plant driving around the site
workers or public on foot
Spotter to be inplace
bunt of work areas where required
SITE RULES & PPE REQUIREMENTS:
Park is at the front of the job, keep access clear for residents,
Ensure you are always wearing the site requirements PPE which is Hardhat, hi vis and
safety boots
NO SMOKING ONSITE:
This includes smoking in front & back of the building !!! -
22nd Paengawhāwhā 2025, WEEKLY BULLETIN 22-04-25
UPCOMING WORKS THIS WEEK:
NOTE:
PART OF BLADE WALL TO BE LEFT STANDING ON EASTERN SIDE OF BLD FOR TEMP SUPPORT TO EXTERIOR WALL
Demo of internal walls, removal of ceiling insulation , door openings etc
KEY HAZARDS:
BRICK WALL , HOLDING UP ROOF VALLEY DO NOT REMOVE UNLESS APPROVED BY PBG
Hazardous Manual Tasks,
Slips, Trips and Falls, Falling
Objects, Cuts and Abrasions,
Use of Electrical Tools and
Equipment, Dust, etc
Exposure to Respirable
Crystalline Silica (RCS) –
inhaling RCS can lead to
silicosis
DISCONNECTIONS :
ACTION-ED PRIOR TO DEMO
water --YES
power---YES
fire --YES
security---YES
A/c ---YES
SERVICES INVESTIGATIONS:
For new wet area connections to existing below floor slab
UNDERGROUND SERVICES :
Before carrying out any underground work, locate services using
Before You Dig Australia, a services locator, non-destructive potholing, potholing by hand
and by taking the other precautions identified in the Code of Practice: Work in the Vicinity of
Overhead and Underground Electric Lines
PERMITS:
Permits are required to be uploaded on hammertech ready for approval prior to any works commencing onsite
FOR:
Demolition
Hot works
Excavation / cutting / coring etc
ELECTRICAL SAFETY:
Temp boards in place for the construction works :
Treat all cables as live if in doubt ASK !
Ensure all leads / tools are tagged
HOUSEKEEPING:
It is everyone's responsibility to insure lunch room & toilets are kept clean.
Ensure everyone places there food / rubbish in the bins and not thrown around site road or gardens
Ensure your work area is cleaned everyday prior to leaving site.
PLANT & EQUIPMENT:
Please ensure all plant is uploaded on hammertech ready for approval prior to bringing to site
WHEN LOADING OUT DURING DEMO BE AWARE :
collision/striking with other
plant driving around the site
workers or public on foot
Spotter to be inplace
bunt of work areas where required
SITE RULES & PPE REQUIREMENTS:
Park is at the front of the job, keep access clear for residents,
Ensure you are always wearing the site requirements PPE which is Hardhat, hivis and
safety boots
NO SMOKING ONSITE:
Client has requested that workers don,t smoke in-front of job site (Bradley st )
Do so, ON THE OPPOSITE SIDE of the road
thank you for your cooperation
Huarere Paemahi Onāianei
Whakahōu Tōmuri i: 6:21 p.m.
Pāmahana: 17C (Taupānga 17C)
Terenga Hau: 9KMH
Mōrahi. Hau: 9KMH @6:21 p.m.
Marangai mai i 9AM: 0.8mm
Tauwāhi Kitenga - Goulburn, NEW SOUTH WALES
Rohe Wā - Sydney Wā Aro Whānui
Matapae - Rāmere, 16 Kohitātea
Showers.
Mōkito: 14C Mōrahi: 20C
Te Tūpono ka Marangai: 80%
Ua Manako: 1 ki 20mm
Tauwāhi Matapae - Goulburn, NEW SOUTH WALES
Rohe Wā - Sydney Wā Aro Whānui
Āpōpō - Rāhoroi, 17 Kohitātea
Shower or two.
Mōkito: 13C Mōrahi: 20C
Te Tūpono ka Marangai: 70%
Ua Manako: 0 ki 5mm
E mōhio ana rānei koe ki ngā Whakaritenga PPE mō tēnei paemahi?
Āta tiaki kei a koe ngā taputapu haumarutanga tika mō tō rā tuatahi i te paemahi.
Tīmata wawe ake ina tae koe ki te paemahi.
Whakaotia tuihonotia tō rēhitatanga paemahi ina pai koe hei penapena tāima.
E mōhio ana rānei koe ki ngā Whakaritenga PPE mō tēnei paemahi?
Āta tiaki kei a koe ngā taputapu haumarutanga tika mō tō rā tuatahi i te paemahi.
Tīmata wawe ake ina tae koe ki te paemahi.
Whakaotia tuihonotia tō rēhitatanga paemahi ina pai koe hei penapena tāima.